Contract details

The Contract Details page gives you a clear, organized overview of a contract’s value and completion date(s).

Updated over a week ago

To access the Contract Details, go to Projects in the Project Explorer, select the relevant Contract, and then click on the Contract Details link (shown on right hand side of Projects Explorer).

When you open the Contract details, the information displayed is determined by your user role and the type of contract. For FIDIC contracts, full visibility requires permissions for both Claims and Variations. For NEC contracts, access to Compensation Events is needed to view the complete contract details. If these roles are not assigned, only partial information will be shown.

Price

  • Original Contract value - The original price of the contract.

  • Confirmed contract value - The original contract value plus any changes that have been approved.

  • Unconfirmed contract value - The confirmed contract value plus all pending changes that have not yet been approved.

ℹ️ Tip: Hover over any value to see how much they have changed.

Completion date

Track progress against contractual timelines:

  • Original completion - The original completion date

  • Confirmed Completion - Approved changes to the completion date

  • Unconfirmed Completion - Changes that have not yet been approved.

ℹ️ Tip: Hover over any value to see how much they have changed.

Sections

The Sections grid shows each section and how its completion date has changed. It shows you the original completion date for each section, the approved changes to it, as well as pending changes.

Key Dates

For NEC contracts, there is a Key Dates grid below the completion dates section. This grid lists all the Key Dates for the contract. For each one, it shows the original completion date, any approved changes, and any changes have not yet been approved.